# Technology Investment Prioritisation Kit

> Fund what matters most from a constrained budget: work in flight reviewed, mandatory work ring-fenced, one financial lens, a scorecard, a cut line, in-year rules.

Source: https://ciohelm.com/toolkits/technology-investment-prioritisation-kit · Area: Decide · Price and packs: https://ciohelm.com/llms.txt

When requests exceed the budget, the loudest sponsor usually wins. This kit runs the annual funding decision on published rules: work in flight reviewed on what is left to spend and gain, mandatory work ring-fenced at its minimum scope, one financial lens with benefits cut by confidence and costs by contingency, a scorecard on fit, complexity, risk and dependencies, a ranked list with a cut line, every committee departure recorded with its gate or trigger, balance, run cost and capacity checks, scenarios at more or less budget, and the in-year rules that keep it true, all filled in for a worked example.

Excel, PowerPoint and Word files. Yours to use and adapt inside your organisation.

## 12 working files, not a slide pack to read

Every file is editable and comes with a worked example for one fictional company, so you start from something, not from a blank page. Workbooks calculate as you type.

### Investment prioritisation workbook (Excel)

15 sheets: setup with your own units and limits, work in flight, requests, financials with NPV, IRR, payback and risk adjustment, the rubric, scoring, ranking, the funding line, committee decisions with gates and triggers, the marginal view, balance with run cost, P&L and capacity, scenarios and the in-year log. A dashboard pulls it together.

### Investment committee deck (PowerPoint)

18 slides: the gap, work in flight, the rules, mandatory work, the ranked list and cut line, departures and deferrals, gates, the marginal view, balance, run cost, capacity, dependencies, scenarios, 2028 commitments and the decisions.

### Scoring and challenge session deck (PowerPoint)

12 slides for the working sessions: ground rules, the four criteria, the financial lens, a worked score, the challenge questions and log, and the requests near the line.

### Investment policy and thresholds (Word)

The principles, who decides what at which amount, the annual cycle and the reserve rules.

### Business case summary (Word)

The two-page summary every request needs, with a do-minimum option, cost confidence, P&L effect and KPIs, worked for a sample request.

### Scoring rubric and guidance (Word)

The four criteria with written anchors, the financial lens, value for money, enabler credit and the pitfalls.

### Benefits and confidence guide (Word)

What counts as a benefit, confidence levels, cost contingency and the sponsor view against the risk-adjusted view.

### Challenge session guide (Word)

How to run the session, the five questions that catch weak cases and the challenge log.

### Investment decision memo (Word)

The filled-in memo: what is funded, departures and deferrals with gates and triggers, and the conditions.

### In-year re-prioritisation and stage-gated funding (Word)

Reserve rules, overruns and underspends, stage gates, new mandatory work and the mid-year cut playbook.

### Investment portfolio canvas (A3) (PDF)

The whole funding decision on one A3 page: a blank template and a worked example.

### Funding what matters most (Guide)

The method in steps with tips and pitfalls, the cycle timetable, using the workbook and the mistakes to avoid.

## Investment prioritisation workbook, sheet by sheet

The workbook carries the method: scores, choices and plans calculate as you type, and the dashboard and deck figures come from it. Click any image to see it full size.

**Dashboard**: Budget, work in flight, mandatory, the line, committed and headroom, balance, run cost and the open checks.

**Funding line**: Every discretionary request down the ranked list, cumulative cost against the budget and where the line falls.

**In-flight**: Work already approved, judged on what is left to spend against what is left to gain: continue, re-scope or stop.

**Decisions**: The rule against the committee decision for every request, with the reason, the gate or the trigger.

## A cut line the committee can defend

The sample company receives 33 new requests asking for EUR 33.3 million against a EUR 26.5 million budget. Work in flight takes 2.4 million off the top, mandatory work 8.8 million and the reserve 1.3 million, leaving 14.0 million for discretionary requests: the line falls at rank 21. The committee makes four departures and three deferrals, each with a gate or a trigger, and commits 24.8 million. New run cost stays inside its ceiling, 30% of the 2028 envelope is already committed, and data and AI skills, at 10.6 FTE needed against 10, become the constraint the roadmap must sequence.

## The method, step by step

### Weeks 1-3 · Call for requests

Publish the policy and thresholds, review work in flight and collect one business case summary per request.

### Weeks 4-5 · Score and challenge

Run the financial lens, score in a panel against the anchors and challenge the cases.

### Week 6 · Rank and test

Draw the cut line, check dependencies, balance, run cost and capacity, and run the scenarios.

### Weeks 7-8 · Decide and run the year

The committee decides and records each departure; the in-year rules handle overruns, gates and cuts.

### Who it is for

- CIOs who must fit more requests than budget into one funding decision
- Investment committees and CFOs who want the same rules for every request
- Portfolio and finance leads running the annual cycle
- Advisers setting up technology investment governance for a client (one licence per client organisation)

### What you need

Excel, PowerPoint and Word, or compatible software. The annual cycle takes about eight weeks; in-year decisions a few hours each.

### Free guides on this topic

- [Technology business case: a structure finance will recognise](https://ciohelm.com/guides/technology-business-case)
- [IT budget: how to build one the CFO will approve](https://ciohelm.com/guides/it-budget)
- [IT steering committee that decides](https://ciohelm.com/guides/it-steering-committee)

## Questions about the kit

**How is it different from the Roadmap Builder?**

This kit decides what is funded and at what stage. The Roadmap Builder then sequences the funded work against dependencies and capacity, quarter by quarter.

**How is it different from the Project Delivery Framework Kit?**

The delivery kit runs one project through its stages and gates. This kit compares all requests against one budget and decides which go ahead.

**Can we change the criteria, weights and limits?**

Yes. Weights, anchors, the hurdle, budget, reserve, run cost ceiling, business units and categories are inputs on Setup.

**Is the company in the example real?**

No. The manufacturer and its figures are fictional. Replace them with your own.

**Is it legal or financial advice?**

No. The templates are practical starting points for management decisions. Have policies and contracts reviewed against the law that applies to your company.